EFFECT ANALYIS AND OPTIMIZATION OF IRREVERSIBILITIES OF EKSERGOECONOMIC COST ON A GAS TURBINE POWER PLANT

dc.contributor.authorDurmusoglu, Yalcin
dc.contributor.authorUst, Yasin
dc.date.accessioned2026-06-27T13:19:43Z
dc.date.issued2013
dc.description.abstractIn this paper a regenerative and irreversible closed cycle gas turbine power plant with pressure loss has been analyzed and optimized according to exergoeconomic performance criterion. The exergoeconomic aim function for optimization is determined as exergy of net power output of the facility per unit total exergy costs. The unit total exergy costs have been combined with investment cost of components, fuel exergetic cost, environmental exergetic cost, exergy destruction cost and stream line exergetic costs. The cost equations have been performed according to a SPECO/ AVCO (Specific Exergy Costing/ Average Costing) method which is mostly used in literature and the results are discussed.en
dc.identifier.eissn1304-7191
dc.identifier.endpage281
dc.identifier.issn1304-7205
dc.identifier.issue2
dc.identifier.startpage263
dc.identifier.urihttps://hdl.handle.net/20.500.14981/51872
dc.identifier.volume31
dc.identifier.wos000219699400011
dc.language.isotur
dc.publisherYILDIZ TECHNICAL UNIV
dc.relation.ispartofSIGMA JOURNAL OF ENGINEERING AND NATURAL SCIENCES-SIGMA MUHENDISLIK VE FEN BILIMLERI DERGISI
dc.subjectBrayton cycle
dc.subjectenvironmental exergetic cost
dc.subjectexergoeconomic analysis
dc.subjectexergy destruction
dc.subjectefficiency
dc.subjectCOMBINED HEAT
dc.subjectEngineering
dc.titleEFFECT ANALYIS AND OPTIMIZATION OF IRREVERSIBILITIES OF EKSERGOECONOMIC COST ON A GAS TURBINE POWER PLANT