dc.description.abstractThis study generates a critical path method approach for the first Green Platform Supply Vessel hull constructed in Turkey. The vessel was constructed and partly outfitted in a Turkish Shipyard and delivered to Norway. The project management of the vessel was conducted utilizing Critical Path Method (CPM) and the critical paths during construction and partly outfitting period of this sophisticated vessel were presented. Additionally, the precautions in order to prevent the delay of the project were discussed.en
dc.identifier.eissn1943-670X
dc.identifier.endpage525
dc.identifier.issue7-8
dc.identifier.startpage515
dc.identifier.urihttps://hdl.handle.net/20.500.14981/52844
dc.identifier.volume20
dc.identifier.wos000330482800005
dc.language.isoeng
dc.publisherUNIV CINCINNATI INDUSTRIAL ENGINEERING
dc.relation.ispartofINTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING-THEORY APPLICATIONS AND PRACTICE
dc.subjectProject Management
dc.subjectProduction
dc.subjectCritical Path Method (CPM)
dc.subjectGreen Vessel
dc.subjectPlatform Supply Vessel
dc.subjectACTIVITY NETWORK
dc.subjectEngineering
dc.titleA CRITICAL PATH METHOD APPROACH TO A GREEN PLATFORM SUPPLY VESSEL HULL CONSTRUCTION